It was
only in my mind to think we could live and sleep in the Knock Down Home we are
building, as first step in our process, last Sunday evening March 15th.
But we could not. The water system was not ready, sewage not fully connected
and we are (still) dealing with a malfunction in the electricity system in the
delivered basic container. So more time needed and we do not want to stress up.
The same
happened with our new internet connection. We heard yesterday it will take till
at least somewhere in April till we can have a connection. So, I cancelled 3BB
(internet connection firm) who changes over and over again the installation
date and does not want to put cables in pipes on the land in the soil. Very
strange because at the resort I am living in Mae Rim they did everywhere.
At the
place and land we are creating our ideas we do not want to have any cable in
the air.
Phatsamon
at the moment is negotiating with other firms to get the job done.
And the
big digging machine… broke down and did not come. We will find another firm
tomorrow.
It took
two more nights in a hotel and last two days we managed to fix our power &
water plant (even with an emergency power unit generator) back up and the
sewage system is connected. All working well now.
Phatsamon
painted the steel construction of the power-plant with grey primer and soon the
walls and roof will be fixed. We also use the space as a storage for some
garden tools.
Thai
people like an outside kitchen. Phatsamon installed a part of it today.
So,
starting today we will live in the basic Knock Down Home. I have to fix the
malfunction of the electricity but I think I will get the job done or find a
solution. Hope we will have internet soon to publish our further stories.