Monday, March 6, 2023

Visible layout of the main house and developments second guest pyramid

The first layer of load bearing wall blocks is in. A lot of measuring, sawing and cutting for the pipes of electricity, sewage and warm-& cold water. This evening, with the laser instrument, we will level all the blocks by planing them with a special tool. 
Actually now the layout of the ground floor of the main house starts to be visible. 

Also we did the tiling on the foundation wall under the veranda to make, made a (partly) temporary stair and fixed several spots of the concrete topping of the floor. 

We did the tiling of the entrance of the second guest pyramid and put the pavement around. 

The three pyramid guard statues are placed on a concrete foundation block.

Yesterday we ordered the interior doors for the house. Special order because we want wider doors than the in Thailand common used ones. 

Our new, two months young now, orphan puppy Singto feels more and more at home at our place. 












Frans Captijn