Electrical installation approved, outside kitchen and grease trap installed, start of building the Labyrinth and ready to install the washingmachine

This afternoon we got a 'GO' from PEA (Provincial Electricity Authority in Surin) for our electrical installation of the control room / pump house and our temporary living space. The installations are approved so soon we get 'normal' power (and price) with a new (final) meter. 

Yesterday first I installed the outside kitchen sink with a special grease trap (to protect the soak-away field from grease and dirt), the place for cooking and the place for the washing machine. All temporary till our main house (in a couple of years) will be finished. 

We also started to build the labyrinth. First the placement of the permanent form work. Today we started with spirit leveling of the form work. During our work dog Joke (family dog of Phatsamon) came to visit Kadhow and us. 

The last couple of days physical work is a real hard job and we need to take many breaks to rest. The afternoons now we have rain showers and thunderstorms (Kadhow very afraid). In the morning high temperatures (around 38 degrees Celsius) in combination with high humidity. 

We have and take the time ;). 

Find some pictures of the last two days.











Frans Captijn