Finally the rain is a bit reducing, temperatures are slowly going down and still tremendous high humidity. Our ricefield and the fields around us are flourishing. Causing my yearly returning hay fever for some weeks.
The dirt road to our site is drying. After this rainy season a lot of damage and deep holes. Still, today and two days ago enough strong for delivery of 3700 bricks and, this afternoon, finally the 21 U-ditches.
We ordered the bricks in Surin but it worked out the factory is in Ayutthaya. A nearly six hour drive for the pickup truck driver to our place to deliver. It took the truckdriver who brought the U-ditches a long time to decide if he, with his crew, should finish his journey to our site because of the road conditions or return and come back later. After talking with Phatsamon and checking the muddy road they decided to give it a try. One of the pictures shows the thick layer of mud they had to pass at the wheels.
Yesterday we picked up the custom made wooden front door frame with our own truck at a wood factory in Surin.
The last week we finished the metal stud wall frames, fixed the basics of the electrical installation of guest pyramid II and connected both pyramids to the outside electricity meters and switchboard.
With blocklaying we make progress now.