Tuesday, November 3, 2020

Concrete for the first guest pyramid drying.

This morning we were one of the first for the company to deliver concrete. Early we prepared everything already. One of the former concrete truck drivers returned and we all were happy to see each other again. The driver was very surprised to see the Labyrinth ready and gave us several compliments of the job done. 

It worked out, after the long rains, the truck only could use the gravel road at our site. Two times it was stuck in the mud. So we had some more work to do (carrying concrete in buckets) for the last part. This is really exercising with 31 degrees C in the shadow and very high humidity after the rains. Hard work for all. Only Kadhow enjoyed the shadow under our temporary house. 

We managed also to pour the concrete for the extra water tank . Phatsamon did not only help with raking the concrete but did all the leveling of the top layer as well. Nice to really do things together.

For the driver the job unfortunately took a bit longer than expected because the marshy land. At the end, with his tip, snacks and a bottle of beer he was happy. 








Frans Captijn


  