We are happy to share, although very high temperatures again, we managed to 'finish' and fix many things the last couple of weeks.
First of all the outside tiling, this afternoon 4,30 PM (Thai time) is 'finished'. All together a bit more than 130 m2. Finished between ' ' because we are still in the process of joint filling now. We have to do that in the evening to give the joints time to harden instead of joint filling drying out by the heat of the sun.
The first short and soft rains appeared but the walls already now are 'waterproof'.
The second thing that is 'finished' is the wooden ceiling of the yoga/meditation Sala on the first floor. We made it from pinewood with a special coating/protection. A lot of work. Some finishing touch still have to be brought in.
Also the Philips floodlights are installed now with a so called 'hotel-switch'. Meaning, you can switch on and off the floodlights upstairs as well as downstairs.
Natural ventilation (Venturi vents) is in between the rooftiles and the wooden planks.
All electricity is installed and/or prepared. The rotating Hatari ceiling fan has to be installed but we will do that later not to offer this fan as a place to create bird nests.
During our ceiling installation a couple of pigeons every night again used the openings between the roof tiles and wood as a place to sleep. Two times we had to take a beginning of a nest, and even two just laid eggs out. Happy they found another place nearby now.
The last (sliding) door at the back side of the house is installed and finished by the village company. A good job they delivered. The same extra thick quality aluminum and also thick black glass. It took two weeks after order because this material is not regular in stock and had to be ordered at 'Metal Thai' in Bangkok.
We used the time between order and installation to finish the concrete space and floor tiles for the sliding door and the entrance of the scrawl space under the house.
The company installed also some rain leakage protection above the top-hung windows.
We created two basis for the outdoor air-conditioning units to be installed in May.
A ten cm thick reinforced concrete plate in a 20 cm high curb. Both places are not connected with the outside walls but 'floating'. We put a one cm. thick polystyrene layer covered with grey silicone in between.
Although the outdoor air conditioning units are fixed to the floor on thick rubbers, I just wanted to be sure we did do all to reduce any noise and vibration of the running aircons inside. Reason why we did not connect the bases to the wall.
Maintenance:
At a night, beginning of March, the main pressure pump of our project water system stopped working. I discovered at 3 AM after visiting the toilet.
Because of 'cooler' temperatures I decided to try to fix the problem in the night. It took over two hours to dismantle a part of the pump and the pressure switch. Chalk, again, caused the problem. After deep cleaning the problem is solved again (for a couple of months).
The siphon of the outside temporary 'kitchen' behind the TED's started leaking. Also the grease trap needed deep cleaning and a new inner basket. Happy I ordered in advance.
I had to renew the siphon and connection to the grease trap, clean the trap and renew the basket. Everything fixed again.
One of the three air conditioning units we already have (into the TED's) started to make a strange noise and a smell of burning.
I cleaned the outdoor unit and also the inside unit. The outdoor unit fan was a bit out of balance because some kind of fly build a mud nest on one of the wings of the ventilation blades. The inside unit was filled with over twenty small eggs of Gecko's. They laid the eggs on the electricity wire connection and we think that caused the smell.
We also checked and cleaned the other two air-condition units.
Everything fixed and working again.
Our Air quality station, connected on the World Wide Web (Aqicn dot org), suddenly stopped transmitting information. After checking it worked out, don't ask me how, a Gecko put some eggs in the monitor unit. One of the eggs was broken and many ants entered the station to 'clean' up and also caused trouble in the electric system of the unit. I cleaned it and took the station for a short while off-line. Happy it's working again.
Last but not least, we fixed the wall of the toilet of the TED's again. Happy we could find nearly the same tiles (Marbella brand) at Global House in Surin. We also changed the tap. This time in a, for us, good quality of Hafele. Not again this frustration as I talked about in the Blog before.
We just got a phone call our Samsung Windfree aircondition units arrived in Surin. We already asked them to install this May after we managed to isolate and install the ceilings inside.
Log story short, all this activities kept us from the street ;).
We think it's time for a short break.
Frans & Phatsamon